NEW ORDERS
CLIENT: Saipem SPA - Italy
END USER: Saipem
PROJECT: Shah Gas Development
PLANT: Abu Dhabi - UAE
TYPE OF BOILER: No.4 Heat Recovery Steam Generators
downstream an Incenerator, with a steam production
of 250 t/h each.
DATE OF ORDER: January 2011
-----------------------------------------------------------------------------------------------
CLIENT: Vinci Environnement - France
END USER: Vernea
PROJECT: Clermont Ferrand
PLANT: Clermont Ferrand - France
TYPE OF BOILER: No.1 Waste To Energy downstream a grate
for urban waste combustion, for steam production of 77 t/h.
DATE OF ORDER: March 2011
-----------------------------------------------------------------------------------------------
CLIENT: Tecnimont SpA - Italy
END USER: Kuwait National Petroleum Company (KNPC)
PROJECT: Acid Gas Removal Plant
PLANT: Mina Al-Ahmadi (MAA) Refinery - Kuwait
TYPE OF BOILER: No.1 Fire Boiler with fuel gas and fuel oil,
for steam production of 182 t/h.
DATE OF ORDER: May 2011
-----------------------------------------------------------------------------------------------
CLIENT: Hellenic Petroleum S. A. - Greece
END USER: Hellenic Petroleum S. A.
PROJECT: New Water Steam Boiler “U-5190”
PLANT: Aspropyrgos Industrial Complex – Attica - Greece
TYPE OF BOILER: No.1 Fire Boiler with fuel oil, for steam
production of 65 t/h.
DATE OF ORDER: September 2011
|